In accordance with the Road Traffic Regulation Act 1984, Reading Borough Council will be putting temporary restrictions in place along High Bridge and Duke Street, see below for full details:

Date and timeRestriction
9 July to 7 November 2024Single lane closure*
9 to 12 July 2024, 2100hrs to 0600hrsOvernight full road closure of High Bridge, part road closure of Duke Street – completed
10 September 2024 at 2100hrs until 13 September at 0600hrs (3 nights)Overnight full road closure of High Bridge, part road closure of Duke Street
4 November 2024 at 2100hrs until 7 November 2024 at 0600hrs (3 nights)Overnight full road closure of High Bridge, part road closure of Duke Street

*During the single lane closures, the bus/taxi lane and parking restrictions will be suspended. A temporary ‘No Waiting at Anytime’ parking restriction will be implemented.

Should the works take longer than expected, the restriction will remain in force until the works are completed with a maximum duration of 18 months. The road closures are necessary to carry out repair works on the bridge. A signed diversion route will be in place throughout.